[ictgov] Fwd comments from Peter Dore on Project Governance
Marghanita da Cruz
marghanita at ramin.com.au
Tue Nov 14 14:55:42 EST 2006
Hi Peter,
Perhaps the concept that is missing is Risk and its management.
From AS8015 (& 4360) -
available at
<http://www.saiglobal.com/shop/script/Details.asp?DocN=AS073376438XAT>
Risk: The chance of something happening that will have an impact upon
objectives. It is measured in terms of consequence and likelihood
(AS/NZS 4360)
Changes in deliverables/scope need to be balanced against objectives...
they could fall short or exceed initial understanding and expectations -
due to developments in the project or external to it...this is business
alignment.
Marghanita
<snip>
> From:
> Peter Dore <pdore at emirates.net.ae>
> Date:
> Sat, 11 Nov 2006 22:33:42 +0400
> To:
> 'Tom Cleary' <tcleary2 at csc.com.au>, 'Rimas Skeivys'
> <rimas at ugovern.com.au>, 'Marghanita da Cruz' <marghanita at ramin.com.au>
>
>
> Hi all,
>
> (Firstly, please note new email. pdore at eim.ae <mailto:pdore at eim.ae> I
> can receive on the old optusnet address however cannot send on it. I
> prefer you send mail to both addresses)
>
> I'd like to add some experiences in to this part of the conversation. I
> have had the role of implementing full SDLC/PM/QA/etc methods and
> processes into a couple of reasonable sized places. I was heavily
> involved in BHP IT a few years ago in Canberra and corporately as
> Corporate PI Manager, and then in a major Saudi Bank where I inherited a
> very large number of half baked projects including some very major items
> to sort out. Add to this my background in Naval engineering and major
> repair projects for warships which is a bonus because of the required
> high discipline levels in PM....
>
> From this experience I will add some comments to Tom's below, marked
> with [PD*** ]
>
> <<snip>>
>
> My observations lead me to believe that there are some drawbacks to
> Project Management models which only seem to get discovered when things
> go too far to avoid additional cost/downtime or other pain.
>
> Meeting User requirements under the strictures of a Sponsor is an
> excellent objective.
>
> However, everyone knows that scope creep tends to boil away budget which
> should be used for some of the "quality" functions ( documentation,
> anyone? ;-) and I think that means we often do not address the whole
> story, leaving some issues to the Business to deal with by other means.
>
> [PD*** One of the, if not the actual, worst managed areas in PM today is
> Requirements. Scope creep is a basic PM skill and is a joint
> Requirements Management / Configuration Management / Management
> Discipline issue. In order to adequately control the budget we need to
> be very careful to avoid scope creep - easily said, however many
> customers and in my recent Qld experience even project directors will
> all too readily add scope and no budget with lame excuses like 'it's
> always there, but we didn't see it before'..... Etc. By ensuring that
> scope items (individual requirements) are carefully identified and
> placed into CM and under change control, then justification has to be
> made, including added budget or offset, or the scope cannot change. This
> is basic and must be placed into project procedures. PRINCE2 adequately
> addresses this in it's CM words, but rarely do we see the discipline
> applied to make it work. PRINCE2 requires discipline, and the trainers
> will tell you this..... Like I mentioned, easily said, but the
> importance is usually seem too late.]
>
> In my experience, this means that instead of using a wide range of
> knowledgeable resources to go looking for issues when reviews occur,
> people tend to get sign off from the Architect, the User rep. and
> Sponsor, then submit the forms for cutover to production ( ... I know,
> ITIL does have the whole "Release Mgmt" thing in this space )
>
> Don't get me wrong, the Project is properly constituted and maintained
> and does not suffer from any unusual stresses that would not be part of
> normal running, so the Management decisions get properly made and approved.
>
> [PD*** This is one area I would question. I cannot agree the project is
> properly constituted and maintained when the need for careful
> requirements control is not maintained and scope creep erodes the budget
> to a significant extent. My experience is similar, but my interpretation
> is that a lack of suitable discipline to properly implement the methods
> and processes is the cause.]
>
> But because the Architect, Users, Sponsors and Project Managers are
> focused on the Project itself, often without full knowledge of other
> Projects, Infrastructure developments or Technology changes, significant
> issues may arise unseen. ( The guy who taught me PRINCE told me of
> "OSINTOTS" == "Oh s**t I never thought of that." - like gremlins )
>
> At that point, it is often discovered that the app. is going to produce
> security problems/network overload/third party costs/whatever which are
> then fudged around because it's too late to fix the problem and the
> project must go live, or it is "out of scope" so the Business has to
> address it in some other way - often by accepting high risks or facing
> the political damage from having a project fail "in public".
>
>
>
> [PD*** The Architect, Users, Sponsors and PMs do focus on their
> projects, but as Tom says so often this is to the detriment of other
> projects and again, the area of Portfolio Management, or perhaps we can
> call it Programme Management, should be instituted to cover this.
> Governance has a real role here and I will come to that later. My
> approach in the Saudi Bank was to critically examine the 93 projects I
> inherited. Many were small and insignificant, many were pet and unfunded
> jobs, some were critical and others in the middle. My instruction was to
> 'implement PRINCE2' as if that was the way to fix the mess. First I
> built 6 programmes of related projects (the Electronic Banking Program,
> the Treasury Programme, etc) and I managed to have clear project
> managers defined for each project. Then made a clear definition of
> Programme Managers for each programme. I trained the Programme Managers
> in the same way as the project managers, and had them produce program
> plans that looked like project plans, but their project was to manage
> the project managers and project interdependencies..... (By project
> plan, I mean Project Management plan, not a MSProject schedule). Then I
> advised the PMO manager to build a similar PMP for the overall
> portfolio, and I purchased a HP A0 plotter so that we could get full
> programme timelines on the one sheet, and show inter project, intra
> programme, and inter programme dependencies all together. This is
> complex, but I am cursed with the ability to see the big picture so it
> had to be communicated to each project and programme manager, to the PMO
> and ultimately to the sponsors and the Board of the bank so that all
> could see the risks and effects of decisions across the full suite of
> work. In this way the necessary compromises that come into all PM work
> can be optimised to reduce cost and schedule overrun. Ultimately the
> projects started to come in closer to schedule and budget, but the cost
> is a lot of work.
>
> So I implemented PRINCE2 as instructed, tailored with guidance to suit
> the varying sized projects, supported by a higher level version to
> manage the programmes in the same manner as the projects, but not quite
> as it had been seen before or expected, and somehow kept my sanity (I
> think). My sponsor was the CEO of the bank which provided support to get
> the initiatives actually in place.]
>
> [PD*** Now to the Governance side of all this. In the back of the mind
> we need to retain the lessons of our failures, and of our successes, and
> ensure that our Governance adequately addresses them. I see a prime role
> of Governance, if not THE prime role, is to objectively verify that all
> the precautions to do with the use of proven methods and processes, and
> management discipline are in place and used, and that short-cutting or
> reduced management is only allowed when the risks and consequences of
> the approach is adequately considered. Governance must ensure that
> method and process tailoring to suit project size and complexity is
> appropriate and that adequate dependency management is carried out at
> the appropriate level.
>
> This is one of the reasons that I was unhappy with guidance in our
> Governance standards where we provided a set of closed questions easily
> answered by saying 'Yes', instead of being answered with adequate
> analysis to provide actual information. I piloted those closed questions
> and was very unhappy with senior Government response as it failed to
> give real information to the effectiveness of the PM or the governance
> being implemented.
>
> My apologies for my extended reply, but I hope this provides some
> thought material.]
>
> Regards
>
> Peter Dore
>
>
>
>
>
>
> ------------------------------------------------------------------------
>
> _______________________________________________
> ICT Governance Forum
> http://listserv.csu.edu.au/mailman/listinfo/ictgov
--
Marghanita da Cruz
Phone: 0414-869202
http://www.ramin.com.au/itgovernance
http://www.ramin.com.au/linux
http://www.ramin.com.au/eco-sydney
More information about the ictgov
mailing list